ARM Platinum

Nkomati Nickel Mine

Located in the Machadodorp area of the Mpumalanga province, 300 kilometres east of Johannesburg Nickel mining takes place by means of an underground shaft as well as by open-pit mining Oxidised chromitite is also mined as part of the pre-strip of the future open pits.

Management The mine is managed as a 50:50 unincorporated joint venture with Norilsk Nickel Africa (Pty) Ltd.
Resources and
Reserves:
(100% basis)
Measured and Indicated Resources Proved and Probable Reserves
Mt Ni% Mt Ni% Moz
Nickel 290.59 0.34 134.89 0.33
Mt Cr2O3% Mt Cr2O3%
Chrome 1.43 31.59 1.16 27.57
Mt g/t 4E Mt g/t 4E Moz
PGMs 290.59 0.85 134.89 0.85 3.68
4E = Platinum + Palladium + Rhodium + Gold
Refining All metal produced is smelted and refined by Metal Trade Overseas AG (MTO).
Total labour 2 744 (includes 1 943 contractors).

Operational statistics

F2008 F2009 F2010 F2011 F11/10
% change
Metal production
Nickel Tonnes 5 136 4 495 9 666 10 100 4
Copper Tonnes 2 605 2 268 5 210 5 210
Cobalt Tonnes 276 244 578 553 (4)
PGMs Ounces 40 813 26 727 52 574 53 610 2
Chrome ore sold 000t 1 146 661 502 335 (33)
Chrome concentrate sold 000t 51 314 381 22
Operational statistics
Tonnes milled Thousand 1 070 1 259 3 308 5 259 59
Head grade % nickel 0.70 0.54 0.45 0.32 (13)
Average number of permanent employees Number 306 560 823 801 (3)
Average number of contractors Number 1 190 2 060 2 100 1 943 (7)
Financial indicators
Nickel on-mine cash cost per tonne treated R/tonne 339 389 242 271 12
Cash cost net of by-products US$/lb (4.45) 2.48 3.26 4.99 53
Net sales revenue R million 1 996 1 086 2 439 2 991 23
Cash operating cost R million 363 490 801 1 423 78
Cash operating (loss)/profit – Total R million 1 192 181 916 824 (10)
Cash operating (loss)/profit
– Nickel Mine R million 518 (253) 584 256 (56)
Cash operating (loss)/profit
– Chrome Mine R million 674 433 332 567 71
Average Nickel price US$/t 28 507 13 312 20 285 23 970 18
Capital expenditure R million 584 1 756 1 202 808 (33)

Refer to note 2 (PDF - 62KB) for Nkomati Nickel Mine segmental informationn.

Nkomati Nickel Large-Scale Project update

Total funds committed at 30 June 2011 amount to R3.5 billion of the total R3.7 billion approved for the capital project. The next phase of the Eskom power supply project is the upgrade of the 132kV overhead distribution lines and we anticipate this to be completed by December 2011. Nkomati’s Eskom Electricity Supply Agreement was concluded in December 2010.

Nkomati Nickel Large-Scale Project update

Platinum division

Platinum Division map

Platinum division map


Partner company

Norilsk Nickel

www.nornik.ru/en