ARM Platinum

Two Rivers Platinum Mine

Description of assets

The mine is located near the town of Steelpoort, in Mpumalanga on the eastern limb of the Bushveld Complex. The operation comprises an underground mine consisting of the Main Decline, the North Decline and a concentrator plant. ARM’s economic interest in Two Rivers is 55%.

Management

The mine is managed by ARM.

Reserves and resources (100% basis)

 Measured and Indicated Resources
PGM+Au
Proved and Probable Reserves
PGM+Au
 Mt(6E) g/tMozMt(6E) g/tMoz
UG254.094.718.1937.293.984.8
Merensky18.73.552.13

4E = Platinum + Palladium + Rhodium + Gold

Refining

All metal produced is smelted and refined by Implats subsidiary Impala Refining Services Limited (IRS).

Number of employees

2  852 (including 2 078 contractors)

Operational review – F2009

Two Rivers completed its first financial year at full production capacity. Tonnes milled increased by 11%. This, together with a head grade improvement, resulted in a 19% increase in PGM ounces in concentrate. At year-end the surface ore stockpile was 207 122 tonnes. As part of the plant optimisation, the secondary crusher and additional cleaning circuit were commissioned during August 2009. Cost-containment initiatives and the postponement of capital expansion projects were implemented as part of a cash-preservation strategy.

The Impala Platinum and ARM Boards have approved a transaction in terms of which Impala Platinum will exchange portions 4, 5 and 6 of Kalkfontein, as well as all Tweefontein prospecting rights, for an additional 4% shareholding in Two Rivers, thereby increasing its stake to 49%. The transaction will become effective pending Section 11 approval from the DMR.

100% basis F2006F2007F2008F2009F09/08
% change
Concentrate production
PlatinumOunces87 93498 621118 02320
PalladiumOunces50 47956 41167 39019
RhodiumOunces14 50116 13019 13619
GoldOunces1 1901 3011 62725
RutheniumOunces24 34227 68335 57718
IridiumOunces5 6516 3457 54119
PGMsOunces 6E184 099206 491246 29519
NickelTonnes25029836523
CopperTonnes11814319033
Operational statistics
Tonnes milledMt2.042.372.6211
Head grade (6E)g/t4.244.004.103
Average number of own employeesNumber47958377433
Average number of contractorsNumber1 4451 6122 07829
Financial indicators
Cash costR/tonne24634039917
Cash costR/Pt pz5 7248 1618 8468
Cash costR/PGM oz 6E2 7343 8984 2399
Cash costR/kg 6E87 906125 319136 2889
Basket price (6E)R/kg268 928362 935246 680(32)
Net sales revenueR million1 4082 3621 022(57)
Cash operating costR million4258051 04430
Cash operating (loss)/profitR million9451 485(83)(106)
Cash operating margin%6963(8) 
Capital expenditureR million957464357346(3)

Refer to note 2 of the financial statements (PDF - 41KB) for Two Rivers segmental information.

Platinum division