ARM Ferrous
 |
 |
|
|
The Ferrous Division performed well in the year, despite extremely volatile market conditions. Higher prices in the
first half were followed by an unprecedented reduction in manganese and chrome volumes sold in the second half. |
|
Divisional structure


 |
Jan Steenkamp
Chief Executive: ARM Ferrous |
Scorecard
| |
|
| |
|
| |
Complete commissioning of the
second phase of the 10 mtpa
Khumani Mine. |
|
|
|
The 10 mtpa Khumani Mine was
commissioned on time, within
budget. |
|
|
|
Achieve 10 mtpa production on an
ongoing basis. |
|
| |
Complete feasibility study for
Khumani Mine expansion, to
16 mtpa. |
|
|
|
Feasibility study completed
and project approval received
from all boards. |
|
|
|
Continue expanding Khumani Mine,
ensuring project remains on time
and within budget. |
|
| |
Finalise additional 4 mtpa iron
ore export contract with Transnet. |
|
|
|
4 mtpa export contract with Transnet
not finalised; changes to type of
locomotives necessitated a review
of parameters. |
|
|
|
Finalise the Transnet contract for
the additional 4 mtpa export
allocation. |
|
| |
Finalise life-of-mine plan for
Beeshoek Iron Ore Mine, for local
contract sales. |
|
|
|
Life-of-mine plan not finalised
due to uncertainty of local
market requirements. |
|
|
|
Explore options for Beeshoek
Mine in terms of local market
opportunities. |
|
| |
|
| |
Finalise manganese export contract
beyond 2009 with Transnet. |
|
|
|
Manganese export contract not
finalised. Transnet commenced a
new process of allocating capacity
via Port Elizabeth harbour. |
|
|
|
Finalise manganese export
contract with Transnet to
commence in November 2009. |
|
| |
Complete Nchwaning Plant
feasibility study (+ 1.5 mtpa). |
|
|
|
Feasibility study completed. Board
approval received and construction
commenced. |
|
|
|
Complete construction of new
processing plant to take total
manganese ore production capacity
to 5 mtpa. |
|
| |
Cato Ridge Works to commence
environmental impact assessment
process for the construction of an
additional furnace (No 7). |
|
|
|
Environmental impact assessment
process delayed due to reassess -
ment of economic viability of furnace
and an accident at the operations. |
|
|
|
Re-evaluation of economic viability
of additional furnace (No 7), and
finalisation of EIA process. |
|
| |
|
| |
Commence process of converting
Dwarsrivier Chrome Mine from
contractor-operator to owneroperator. |
|
|
|
Conversion successfully completed. |
|
|
|
Establish ARM/Assmang culture
with new workforce and improve
operational efficiencies. |
|
Operational overview – attributable to ARM
| |
|
|
|
|
|
|
|
|
|
|
|
|
Operational |
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
target |
|
| |
Sales volumes |
|
|
|
|
F2008 |
|
|
|
% change |
|
|
F2010 |
|
| |
Manganese ore |
|
000t |
|
|
1 076 |
|
|
|
1 856 |
|
|
|
(42) |
|
|
|
|
| |
Nchwaning* |
|
000t |
|
|
794 |
|
|
|
1 641 |
|
|
|
(52) |
|
|
 |
|
| |
Gloria* |
|
000t |
|
|
282 |
|
|
|
215 |
|
|
|
32 |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
Ferromanganese* |
|
000t |
|
|
59 |
|
|
|
124 |
|
|
|
(52) |
|
|
 |
|
| |
Iron ore |
|
000t |
|
|
3 704 |
|
|
|
3 291 |
|
|
|
12 |
|
|
|
|
| |
Khumani |
|
000t |
|
|
2 908 |
|
|
|
557 |
|
|
|
422 |
|
|
 |
|
| |
Beeshoek |
|
000t |
|
|
796 |
|
|
|
2 734 |
|
|
|
(71) |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
Chrome |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
Dwarsrivier chrome ore* |
|
000t |
|
|
128 |
|
|
|
152 |
|
|
|
(16) |
|
|
 |
|
| |
Machadodorp charge chrome |
|
000t |
|
|
72 |
|
|
|
138 |
|
|
|
(48) |
|
|
|
|
| |
ARM Ferrous operating margin |
|
% |
|
|
63 |
|
|
|
55 |
|
|
|
|
|
|
|
|
| |
ARM Ferrous cash operating margin |
|
% |
|
|
68 |
|
|
|
61 |
|
|
|
|
|
|
|
|
| |
Headline earnings attributable to ARM |
|
R million |
|
|
3 150 |
|
|
|
2 775 |
|
|
|
14 |
|
|
|
|
* Excludes intra-company sales.
Review of the year
The Ferrous Division performed well in the year, increasing
headline earnings attributable to ARM by 14% to R3 150 million,
despite extremely volatile market conditions. In the first six
months of the year, a commodity bull run supported prices of
the division's products, with an unprecedented reduction in
volumes sold during the second six-month period. Under these
very difficult conditions, the Ferrous Division succeeded in
widening cash operating margins from 61% to 68%.
With the exception of iron ore, volumes sold in all the division's
commodities decreased compared to the previous financial
year. However, revenue rose to R15.26 billion from R14.83 billion
for F2008 because of higher US Dollar prices and a weaker
Rand. Iron ore sales increased from 6.58 mtpa to 7.41 mtpa
mainly due to an increase in iron ore volumes sold from the new
Khumani Mine.
The operating costs of all operations, except iron ore, increased
at rates in excess of inflation as a result of the rapid downturn
in the economy which led to a significant reduction in sales
volumes. The costs of the iron ore business decreased by 7%,
due mostly to an increase in volumes sold.
The construction and commissioning of the 10 mtpa Khumani
Mine was completed in February 2009, 7% below budget and
ahead of schedule.
Assmang cost and EBITDA margin performance
| |
|
F2009 cost |
|
F2009 |
|
| |
|
increases |
|
EBITDA |
|
| |
Commodity group |
R/tonne |
|
margin (%) |
|
| |
Iron ore |
(7) |
|
70 |
|
| |
Manganese ore |
19 |
|
81 |
|
| |
Manganese alloys |
38 |
|
62 |
|
| |
Charge chrome |
37 |
|
22 |
|
ARM Ferrous sales volumes from 2005 to 2012
(100% basis)
|
* Excluding intra-group sales.
Iron ore
The iron ore division achieved contractual sales of 7.41 mpta
due mainly to robust Chinese demand. The Khumani Mine has
commenced the ramp-up to production of 10 mtpa by July 2011,
which is aligned with the Transnet capacity expansion programme.
The Beeshoek Iron Ore Mine reduced production in line with
total contracted sales and export capacity allocation. Most of
the workforce employed at the Beeshoek operation has been
successfully trained and redeployed to the Khumani Iron Ore
Mine. Most mining activities at Beeshoek Mine ceased and
production was achieved from previous stockpiles and dumps
established during the mining life of Beeshoek.
Manganese
In line with demand, sales of manganese ore decreased from
3.7 mtpa in F2008 to 2.2 mtpa in F2009. Production volumes
were largely steady at 3.13 mtpa (F2009) from the previous
year's 3.15 mtpa. The strategy to maintain production was
to restock, due to the high volumes sold during F2008. After
achieving critical stockpile levels, production was cut back in line
with demand in the last quarter of F2009. Management of the
manganese mines engaged with the workforce to commence a
process of redeploying employees to the iron ore division which
required additional people for the increased production as part
of the ramp-up of the Khumani Mine.
 |
|
 |
| Khumani plant at night |
|
Operating costs at the manganese mines increased by 19%
year-on-year. This was due to higher electricity prices and
an increase in production tonnage from the more expensive
Nchwaning 2 mine to ensure availability of high quality product
for an over-supplied market. Excessive labour costs also
contributed to the increased costs due to the recruitment of
additional labour for the introduction of continuous operations
which was halted when the demand slowed.
Profit margins in the steel industry came under pressure in
the year, prompting a shift towards lower-grade, less costly
manganese. As a result, sales tonnes from the low-grade
Gloria Manganese Mine increased by 31%, with a similar
increase in production volumes. This facilitated below inflation
cost increases at Gloria.
At the Cato Ridge Works production volumes were reduced in
line with the significant drop in demand and some furnaces were
shut down, equating to approximately 40% of capacity shut
down since October 2008. Tonnages sold decreased by 52%
from 247 000 in F2008 to 117 000 in F2009. However, the cost
of pro duction increased by 38% due to sharp electricity cost
increases and the reduction in volumes produced. A decision
was made to accelerate capital expenditure related to improving
furnace efficiencies and environmental legislation compliance
while some furnaces were shut down. As part of the group-wide
cost-optimisation exercise, management at Cato Ridge Works
have identified a number of areas where operating costs could
be reduced, such as reducing the number of full-time employees
and contracting labour as well as improving the efficiencies of
the furnaces.
Chrome
The performance of the chrome division was materially affected
by the decrease in demand for chrome ore and charge chrome,
which are used in the production of stainless steel.
Dwarsrivier Chrome Mine was successfully converted from a
contractor-operated to an owner-operated mine. During the last
quarter of the financial year both the Machadodorp Works and
the Dwarsrivier Mine engaged with the workforce in a process
to reduce the total number of employees as part of a major cost-reduction
exercise in an attempt, in the short-term, to minimise
operating losses.
At Machadodorp Works production capacity was reduced in line
with lower demand for charge chrome. This resulted in furnaces
being shut down, which also led to a reduction in production
levels at the Dwarsrivier Chrome Mine.
Mining rights status
The 10 mtpa Khumani Iron Ore Mine, operating under a new order
mining licence, is in the process of updating its licence to operate
a 16 mtpa mine. All conversion applications for the Ferrous
Division's operating mines - Dwarsrivier Chrome Mine, Nchwaning
Manganese Mine, Gloria Manganese Mine and Beeshoek Mine -
were submitted prior to the 1 May 2009 deadline.
Safety and health
The Ferrous Division achieved its safety targets at most of its
operations during F2009. These included achieving 1.3 million fatality free shifts at Machadodorp Works and 2.8 million fatality
free production shifts at Black Rock Mine. The division achieved
an overall lost time injury frequency rate (LTIFR) of 3.29 in
F2009 compared to 4.9 in F2008. Beeshoek Iron Ore Mine
and Machadodorp Works had an excellent year in terms of
safety, with the last fatalities at these operations in March
2003 and January 2004 respectively. Both achieved in excess
of one million fatality free shifts. Beeshoek Iron Ore Mine
and Machadodorp Works were placed second and third
respectively in the 'Excellence in Safety' competition in the ARM
Group. Cato Ridge Works' safety record improved significantly
in the year and was placed second in the competition.
Regrettably, four fatalities occurred during the year: two at
Khumani Mine, one at Black Rock Mine and one at Dwarsrivier
Mine. A contract security guard at Khumani died from smoke
inhalation from a fire he made in a mobile guard room. A driver
was fataly injured when his dump truck collided with a similar
vehicle on the Bruce haulroad at Khumani Mine. Two employees
were fataly injured in separate fall of ground incidents at Black
Rock and Dwarsrivier Mines.
All operations conduct medical surveillance of employees in
accordance with the requirements of relevant legislation. An
inquiry into possible causes of manganism has been completed
and a report from the chairman of the inquiry is expected in the
near future.
Logistics
The contractual agreement with Transnet to increase iron ore
exports to 14 mtpa through the port of Saldanha Bay is being
finalised. Along with other producers and Transnet, ARM Ferrous
is investigating the possible expansion of the iron ore corridor to
handle in excess of 60 mtpa.
ARM Ferrous is also participating with Transnet in a capacity
allocation process to finalise future manganese export tonnages.
It is anticipated that the short-term allocation process will be
completed towards the end of the 2009 calendar year, while the
long-term allocation process will be finalised during 2010.
Capital expenditure
Assmang's total capital expenditure was R2.8 billion of which
R1.4 billion was attributable to ARM (F2008: R2.9 billion). The
main expenditure items include the completion of the new
Khumani Mine (R924 million) and construction of the Nchwaning
benefication plant (R161 million), which is expected to be
commissioned in March 2010. At Cato Ridge, R296 million was
spent on rebuilding furnaces and on control of fume emissions at
the Cato Ridge and Machadodorp Works, R383 million on mining
fleet enhancements, R191 million on housing and R165 million on
various capital replacement items.
Prospects
The downturn in the world economy, with the resultant reduction
in demand for steel, has had a significant impact on the earnings generated by the Ferrous Division. This is likely to continue to be
the case. However, there are early signs of increased demand
and production will be ramped up accordingly.
Iron ore sales volumes for the new financial year are expected
to reach 9.8 million tonnes, with all export volumes coming from
Khumani and local sales being sourced from Beeshoek.
The Ferrous Division will continue with its growth strategy,
albeit at lower margins in the short-term, helped by steps taken
in the past seven years to make the business more efficient.
These include capital spent on more cost-effective infrastructure
development (such as Nchwaning 3, Dwarsrivier Mine, Khumani
Mine, and the upgrade of furnaces) as well as prudent investment
in human resources and equipment. These capital investments
have significantly improved operating efficiencies, resulting in
the operations being well benchmarked on the cost curve for
comparable global producers.
The Ferrous Division is also working to become an employer of
choice over the next two years. To achieve this, a number of
criteria need to be further enhanced through defined actions
which cover areas such as community investment and involvement,
remuneration and housing.
A key objective remains the further expansion of the Khumani
Iron Ore Mine to 16 mtpa, within budget and on schedule.
The future earnings of the manganese division are dependent
on the export capacity allocation it receives from Transnet and
the short-term allocation (2009 - 2013) will only be decided
towards the end of the 2009 calendar year. Demand from potential
new manganese producers is unclear and so it is uncertain how
much capacity will be allocated to the Ferrous Division through
Port Elizabeth. Assmang, Transnet and other producers are
currently evaluating various options to increase manganese
export capacity from South Africa.
Market review
The past financial year was a tale of two halves. Until October
2008, when the extent of the global financial and economic crisis
first became apparent, sales volumes were strong and prices
for our commodities were at high levels. Thereafter, production
of both carbon and stainless steel dropped sharply, affecting
demand for the products from all three divisions. Two of our
main markets, the USA and Europe, have recently started to
show signs of stabilisation after months of decline. China - after
several months of reduced production - successfully stimulated
its economy and by June 2009 production of steel was again
running at record levels.
Iron ore
Spot prices for iron ore in China fell dramatically after the start
of the financial crisis which meant that much high-cost domestic
Chinese iron ore capacity could no longer compete and was
mothballed. This then pushed up demand for imported ore.
Pricing in the iron ore market is in a state of transition. The
traditional annual benchmark pricing system is under threat,
particularly in China. Settlements over the last two years have
included quarterly and index pricing in addition to spot sales.
Major iron ore producers are split on their views as to whether
an indexing pricing method should replace the benchmark. For
the last quarter of the year under review, provisional prices were
agreed at levels 45% and 33% lower than the previous year
for lump and fines respectively. Although negotiations are still
continuing we expect that these levels - especially in China -
will prevail for contractual tonnages for the first three quarters of
the new financial year.
Ferrous pricing trends for F2009
Manganese
The change in the fortunes of the manganese division was
dramatic. Requirements for ore and alloy virtually disappeared
for a period while our customers reduced their production levels
as demand evaporated. There was also a period of de-stocking
when apparent demand was even lower than actual demand
and our customers tried to reduce their stocks of high-cost raw
materials. Demand for manganese ore then picked up in the
last quarter of the financial year, with substantial exports into
China and the rest of Asia. This trend appears sustainable as
purchasers in the rest of the world are now also indicating that
they need to replenish stocks. During the year, manganese ore
prices plunged to less than 25% of the record levels that were
reached in mid 2008. However, recently there have been signs
of a slow price recovery as high-cost, marginal producers have
exited the market.
Manganese alloys were also badly affected by the credit
crisis, and production and sales volumes, as well as prices, fell
steeply. The alloy industry responded quickly and decisively as
producers closed or cut production. Towards the end of the
final quarter we saw increased demand and some minor price
recovery. The outlook for our manganese alloys in the new year
is dependent on both a recovery of steel production outside
China and continued production restraint from major Western
alloy producers. However, the low prices have meant that China
has sharply reduced alloy exports to the West.
Ferrochrome
Like manganese, the chrome division was badly affected.
Stainless steel production for the second half of calendar 2008
was down over 26% and was even lower in the first half of
calendar 2009. Production now seems to have bottomed out,
but only China and some of the other Asian economies are
producing strongly.
This significant reduction in stainless steel production had a
catastrophic effect on the ferrochrome market, with demand by late
2008/early 2009 dropping to almost zero for a period, and prices
falling by well over 60%. As a result, ferrochrome production -
particularly in South Africa - was slashed to balance the market.
The earlier-than-expected upturn in the stainless steel market,
particularly in China, then coincided with the South African winter
electricity tariff increase. This has meant that a significant number
of furnaces were out of operation for maintenance and the
ferrochrome market has tightened, with stocks low. However, there
are concerns that an expected rapid ramp-up of production after
the winter period may coincide with Chinese stainless steel
production being moderated to reflect real consumption.
 |
| Stockpiling of iron ore prior to railing at Khumani Iron Ore Mine |
|
|
 |
Drill-rig and crew at
Khumani Iron Ore Mine |
|
ARM Ferrous Operational Statistics
Iron Ore Division
Beeshoek and Khumani Iron Ore Mines
| |
Management |
| |
Reserves and Resources |
|
Beeshoek |
|
109.7 million tonnes at 63.71% iron |
| |
- Measured and Indicated |
|
Khumani |
|
632.9 million tonnes at 64.56% iron |
| |
Reserves and Resources |
|
Beeshoek |
|
45.2 million tonnes at 64.95% iron |
| |
– Proved and Probable |
|
Khumani |
|
565.8 million tonnes at 64.49% iron |
| |
Total labour |
|
2 003 (including 1 012 contractors) |
Refer to page167 for Iron Ore segmental information.
| |
|
|
|
|
|
|
|
|
|
F09/08 |
|
| |
|
|
|
F2006 |
|
F2007 |
|
F2008 |
|
% change |
|
| |
Attributable headline earnings |
R million |
|
199 |
|
340 |
|
390 |
|
1 080 |
|
177 |
|
| |
Operating margin |
% |
|
39 |
|
44 |
|
39 |
|
60 |
|
|
|
| |
Total iron ore sales |
000t |
|
5 926 |
|
6 855 |
|
6 582 |
|
7 409 |
|
13 |
|
| |
Iron ore produced |
000t |
|
5 536 |
|
6 675 |
|
4 493 |
|
2 658 |
|
(41) |
|
| |
Iron ore sold |
000t |
|
5 926 |
|
6 855 |
|
5 466 |
|
1 593 |
|
(71) |
|
| |
Sales revenue |
R million |
|
1 411 |
|
2 164 |
|
2 282 |
|
1 284 |
|
(44) |
|
| |
Total costs |
R million |
|
857 |
|
1 197 |
|
1 218 |
|
361 |
|
(70) |
|
| |
Operating profit |
R million |
|
554 |
|
967 |
|
1 064 |
|
923 |
|
(13) |
|
| |
Capex |
R million |
|
346 |
|
94 |
|
100 |
|
160 |
|
60 |
|
| |
Iron ore produced |
000t |
|
– |
|
– |
|
1 848 |
|
6 646 |
|
260 |
|
| |
Iron ore sold |
000t |
|
– |
|
– |
|
1 115 |
|
5 817 |
|
422 |
|
| |
Sales revenue |
R million |
|
– |
|
– |
|
493 |
|
3 733 |
|
657 |
|
| |
Total costs |
R million |
|
– |
|
– |
|
478 |
|
1 576 |
|
230 |
|
| |
Operating profit |
R million |
|
– |
|
(6) |
|
15 |
|
2 157 |
|
14 280 |
|
| |
Capex |
R million |
|
– |
|
1 641 |
|
2 131 |
|
1 369 |
|
(36) |
|
Khumani expansion project
Manganese Division
Nchwaning and Gloria Manganese Mines and Cato Ridge Ferromanganese Works
| |
Management |
|
| |
|
|
| |
|
|
|
Nchwaning |
|
|
|
|
|
|
|
|
Gloria |
|
|
|
|
|
|
|
| |
Reserves and Resources |
|
|
Seam 1 |
|
130.6 |
|
45.1% |
|
9.04% |
|
|
Seam 1 |
|
53.3 |
|
38.2% |
|
5.5% |
|
| |
– Measured and Indicated |
|
|
Seam 2 |
|
180.5 |
|
42.4% |
|
15.50% |
|
|
Seam 2 |
|
29.4 |
|
29.9% |
|
10.1% |
|
| |
Reserves and Resources |
|
|
Nchwaning |
|
109.4 |
|
45.1% |
|
9.04% |
|
|
|
|
|
|
|
|
|
|
| |
– Proved and Probable |
|
|
Gloria |
|
41.0 |
|
38.2% |
|
5.50% |
|
|
|
|
|
|
|
|
|
|
| |
Total labour |
|
|
2 943 (including 834 contractors) |
Refer to page167 for Manganese segmental information
| |
|
|
|
|
|
|
|
|
|
F09/08 |
|
| |
|
|
|
F2006 |
|
F2007 |
|
F2008 |
|
% change |
|
| |
Attributable contribution to headline |
|
|
|
|
|
|
|
|
|
|
|
|
| |
earnings |
R million |
|
163 |
|
288 |
|
2 043 |
|
1 963 |
|
(3) |
|
| |
Operating profit margin |
% |
|
25 |
|
33 |
|
64 |
|
78 |
|
|
|
| |
Manganese ore produced |
000t |
|
2 572 |
|
2 847 |
|
3 154 |
|
3 138 |
|
(1) |
|
| |
Manganese ore sales* |
000t |
|
1 678 |
|
2 327 |
|
3 711 |
|
2 152 |
|
(42) |
|
| |
Revenues* |
R million |
|
994 |
|
1 310 |
|
6 796 |
|
6 308 |
|
(7) |
|
| |
Total costs |
R million |
|
586 |
|
858 |
|
2 060 |
|
1 355 |
|
(34) |
|
| |
Operating profit |
R million |
|
408 |
|
452 |
|
4 736 |
|
4 943 |
|
5 |
|
| |
Capex |
R million |
|
156 |
|
174 |
|
218 |
|
567 |
|
160 |
|
| |
Manganese alloys produced |
000t |
|
309 |
|
347 |
|
261 |
|
216 |
|
(17) |
|
| |
Manganese alloys sold |
000t |
|
260 |
|
251 |
|
247 |
|
117 |
|
(53) |
|
| |
Sales revenues |
R million |
|
1 015 |
|
1 380 |
|
2 756 |
|
2 128 |
|
(23) |
|
| |
Total costs |
R million |
|
915 |
|
931 |
|
1 332 |
|
883 |
|
(34) |
|
| |
Operating profit |
R million |
|
100 |
|
449 |
|
1 424 |
|
1 246 |
|
(13) |
|
| |
Capex |
R million |
|
83 |
|
123 |
|
293 |
|
286 |
|
(2) |
|
* Excluding intra-group sales.
 |
| Khumani Iron Ore Mine |
Chrome Division
Dwarsrivier Chrome Mine and Machadodorp Ferrochrome Works
| |
Management |
| |
Reserves and Resources |
|
53.2 million tonnes at 39.56% Cr2O3% |
| |
- Measured and Indicated |
|
|
| |
Reserves and Resources |
|
39.6 million tonnes at 39.5% Cr203% |
| |
– Proved and Probable |
|
|
| |
Total labour |
|
1 471 (including 269 contractors) |
Refer to page167 for Chrome segmental information.
| |
|
|
|
|
|
|
|
|
|
F09/08 |
|
| |
|
|
|
F2006 |
|
F2007 |
|
F2008 |
|
% change |
|
| |
Attributable headline earnings |
R million |
|
(32) |
|
38 |
|
342 |
|
107 |
|
(69) |
|
| |
Operating profit margin |
% |
|
(3) |
|
9 |
|
38 |
|
15 |
|
|
|
| |
Chrome ore produced |
000t |
|
526 |
|
710 |
|
849 |
|
684 |
|
(19) |
|
| |
Chrome ore sold* |
000t |
|
178 |
|
172 |
|
304 |
|
256 |
|
(16) |
|
| |
Sales revenues* |
R million |
|
68 |
|
79 |
|
177 |
|
337 |
|
90 |
|
| |
Operating profit |
R million |
|
(6) |
|
(12) |
|
(3) |
|
45 |
|
1 600 |
|
| |
Capex |
R million |
|
59 |
|
122 |
|
68 |
|
127 |
|
87 |
|
| |
Charge chrome produced |
000t |
|
230 |
|
242 |
|
270 |
|
169 |
|
(37) |
|
| |
Charge chrome sold |
000t |
|
210 |
|
232 |
|
275 |
|
144 |
|
(48) |
|
| |
Sales revenues |
R million |
|
870 |
|
1 195 |
|
2 331 |
|
1 473 |
|
(37) |
|
| |
Total costs |
R million |
|
893 |
|
1 069 |
|
1 382 |
|
1 242 |
|
(10) |
|
| |
Operating profit |
R million |
|
(23) |
|
126 |
|
949 |
|
231 |
|
(76) |
|
| |
Capex |
R million |
|
61 |
|
77 |
|
90 |
|
270 |
|
200 |
|
* Excluding intra-group sales. |