ARM strategy and key growth projects

Goedgevonden Mine Coal Handling Processing Plant (CHPP)

ARM strategy

ARM Strategy

Key growth projects

  Khumani Iron Ore
(10 – 16 mtpa)
Goedgevonden
Thermal Coal
Nkomati Nickel
Large-Scale Expansion
Konkola North
Copper Project
Steady state16 mtpa 3.8 mtpa local;
3.2 mtpa export
20 500 tpa nickel 45 000 tpa copper
Capex committed75% 99% 95% 82%
StageRamp-up Full production Ramp-up Construction
Position on cost curve30th percentile 25th percentile 40th percentile 45th percentile
Commissioning
(financial year)
2011 2009 2009 2012
Full production2013 2012 2014 2015
Comment Efficient low
unit cost
Dragline opencast
operation
C1 cash cost net
of by-products of
US$4.40/lb at steady
state in 2014
New commodity in
portfolio and first mine
outside South Africa

Project pipeline and operations

Project pipeline and operations

A balanced, growing portfolio


A balanced, growing portfolio